Client: Wagners Service Provider: SWIA (SEQ Team) Project Type: Weighbridge Refit and Di...
Relocation and Commission of Weighbridge for a Holcim Quarry in Nerimbera. Australasia Scales recently project managed the installation and commissioning of the Holcim, Nerimbera Quarry weighbridge located within the Rockhampton, QLD region. The 24m above ground weighbridge required new foundations and access ramps to be constructed prior to commissioning. As part of the installation
A Split Deck Weighbridge, 40 metres long was recently installed at a large Quarry in Millmerran, QLD. The twin deck weighbridge comprises two individual weighbridge decks 20 metres long per section, and was installed end-to-end. Split weighing in this case is the process used for weighing the truck and trailer/s in two halves, and
A Single Deck Weighbridge, 26m long was recently installed at the Alex Fraser site on the north side of Brisbane. With strict time frames and a deadline to meet, Australasia Scales experienced project management team was called into action, a plan was set-out, all milestones achieved in a timely manner, and the project completed within
The weighbridge was installed almost 2 decades ago, and recently failed due to severe lightning strikes experienced across the South East QLD region towards the end of NOV 2013. The replacement weighbridge load cells were fitted in less than 24 hrs, with Australasia Scales technicians working around the clock to ensure downtime was limited